We met with the Electrician this morning to review our Electrical plan prior to him commencing the wiring. We made a few minor changes, mostly to hat switches turn of what lights etc. The ducted air con was being installed while we were there too, those boys just walked freely around on the roof trusses as if they were in the circus!
Plasterers and Bricklayers are booked for next week and should take around 2 weeks onsite. Then our Timber Floor layers will be at the house for approx 3 weeks to complete their job which will bring us up to Christmas.
The builder is hoping to have everything locked up by Christmas, with end of March still for Handover.
It seems to be moving quite fast but the Christmas shut down will probably feel like it is dragging out... Still March is pretty good timing. ;-)